砾石有两种出售方式,按立方码和按吨出售,除非您了解材质,否则两者不一致。该计算器将长度乘以宽度乘以深度得出体积,然后使用您挑选的砾石、碎石、豌豆砾石或沙子的松散堆积密度转换为吨。

当你有体积时,按重量排序:每立方码松散砾石 1.4 吨是常见的转换,碎石稍重,沙子又较轻。

假设前提

  • Volume is length times width times depth, with all inputs converted to feet.
  • Cubic yards are cubic feet divided by 27.
  • Tons apply the loose bulk density for the selected material: gravel 1.4, crushed stone 1.6, pea gravel 1.5 and sand 1.35 tons per loose cubic yard.

常见错误

  • 订购的吨位数来自不同材料的密度,并且偏差 20% 或更多。
  • 忘记了以英寸为单位的深度输入会驱动方量,因此 4 英寸垫和 4 英尺垫相距 12 倍,不相等。
  • 按目测而不是数量购买,然后在项目结束时有一个半交付的垫。

深度指南

购买指南

Gravel is bought by two different units depending on the supplier, cubic yards or tons, and the two only agree once you know the density of the specific material being delivered. This calculator starts from length, width and depth to get a volume, then applies the loose bulk density of whichever material you select, gravel, crushed stone, pea gravel or sand, to convert that volume into a weight. The depth input matters more than it looks: because it is entered in inches and multiplied through the same formula as length and width in feet, a 4 inch pad and a 4 foot pad are 12 times apart in volume, not a rounding difference, so it is worth double checking that field before trusting the output. Delivered depth also settles under compaction, sometimes meaningfully, so a pad ordered at the exact calculated volume can come up slightly short once it is tamped down.

Density is the part of the formula that trips people up, because a single "tons per yard" figure does not exist across materials. Crushed stone runs heavier at roughly 1.6 tons per loose cubic yard, plain gravel around 1.4, pea gravel near 1.5, and sand lighter still at about 1.35, so the same volume of two different materials can differ in delivered weight by more than 15 percent. Sand's lower density also means a sand base requires compaction in thinner lifts than crushed stone to avoid soft spots. That spread is exactly why this calculator asks for a material type rather than returning one generic tonnage figure, and why comparing supplier quotes properly means converting everyone's number to the same unit before deciding who is cheaper.

A gravel base under a fence post or along a fence line is typically a modest 3 to 4 inches, there mainly for drainage rather than structural support, which keeps the volume and tonnage low compared to a driveway or parking pad job using the same calculator. Posts set in gravel instead of concrete rely on free-draining, sandy or rocky soil to hold properly, which is the tradeoff: less rigid than a concrete collar, but better drainage in ground where standing water around the base would otherwise be the bigger problem. Compaction in lifts rather than one pour helps the finished depth stay closer to the ordered volume on larger pads. The post spacing guide and the fence materials guide both touch on when a gravel-only footing is the right call versus when concrete is worth the extra step.

Gravel and concrete are usually compared directly for the same hole, and the fence post concrete calculator runs that comparison from the concrete side using the identical hole dimensions this tool accepts. The embedment depth both approaches need in the first place comes from the fence post depth calculator, and the full reasoning behind choosing one fill material over the other is laid out in the post depth and setting guide. For a bag-based order instead of a tonnage order, the concrete bags calculator covers the same volume logic in bags rather than tons, and if the project also includes a block retaining wall, the retaining wall calculator handles the drainage stone behind it using this same material density approach. The post count driving how many footings need gravel in the first place comes from the fence post calculator, and the rest of the foundation tools sit under the foundation calculators category.

Delivery logistics are worth factoring in alongside the volume and tonnage numbers this calculator produces, since gravel is heavy enough that access matters as much as quantity. A dump truck delivery to a driveway is straightforward, but gravel destined for a backyard fence line or a retaining wall drainage trench often has to be moved by wheelbarrow from a drop point at the curb or driveway, which is worth planning for separately from the tonnage figure itself. Smaller orders, especially for a short run of post holes, are sometimes more practical bought in bags from a home improvement store rather than through a bulk supplier, even though the price per ton is higher that way, simply because a bulk delivery minimum can exceed what a small fence project actually needs. Material choice interacts with purpose as much as with density: crushed stone with angular faces locks together better under compaction than smooth, rounded pea gravel, which is one reason crushed stone is the more common choice under a structural base like a retaining wall footing, while pea gravel or washed gravel is more often chosen for drainage layers or decorative surface applications where interlock matters less than drainage and appearance. None of these choices change the volume-to-weight formula this calculator applies, but they do change which material row in the selector is the right one to pick for a given part of the project.

常见问题

40 x 4 英尺、4 英寸的垫需要多少吨砾石?

体积为 40 x 4 x 0.333 英尺,即 53.3 立方英尺,即 1.98 立方码。按每立方码 1.4 吨的砾石计算,约为 2.77 吨,因此为了安全起见,订购大约 2.8 吨。

砾石公式是什么?

将长度乘以宽度乘以深度(以英尺为单位的深度等于英寸除以 12)得到立方英尺,除以 27 得到立方码,然后乘以材料密度(以吨/立方码为单位)得到重量。

为什么碎石和豌豆砾石的吨位不同?

因为它们的松散堆积密度不同:碎石堆积重约每立方码 1.6 吨,豌豆砾石接近 1.5,普通砾石 1.4,沙子只有 1.35。相同的体积,不同的重量,这就是为什么不存在单一的“吨/码”数字。

我应该按码还是按吨订购碎石?

供应商根据产品和地区报价任一单位,因此要比较报价,您需要两个单位:垫的体积和密度预测的重量,这正是该计算器并排返回的值。

栅栏下的砾石基底应该有多厚?

3 到 4 英寸的底座是混凝土前的栅栏线或柱底座或砾石立柱的常见深度,并且此计算器直接接受以英寸为单位的深度。

我可以用砾石而不是混凝土来设置栅栏柱吗?

是的,在自由排水的沙质或岩石地面砾石回填工程和排水沟中,一些建筑商出于经济和排水的考虑更喜欢这样做。它的刚性不如混凝土,因此在排水比刚性更重要的情况下选择它。

4 英寸的 10 x 10 棚垫需要多少砾石?

0.333 英尺处的 100 平方英尺等于 33.3 立方英尺,即 1.23 立方码,约为 1.73 吨标准砾石。这是该计算器针对任何垫层尺寸重现的简短答案。

砾石是否需要压实深度或交付深度?

交付的深度在压实情况下会稳定下来,有时会达到四分之一或更多,因此请在垫层上规划一些额外的深度并分层压实。将计算器的体积视为清洁表土工作的预压实方量。